Update November 1st, 2021

November 1st, 2021

20211011-site-map
dji_0011

The future Tailings Management Facility (TMF) footprint includes the TMF Laydown area where the offices for the TMF Construction Team are located. The TMF Perimeter Access Road provides access to the TMF area, facilitating construction of the TMF. 

Planned activities for the week of November 1st include Tree Clearing, continuing to advance the Early Earth Works within the Kenogamisis and S4 Aggregate Pits, installation of light fixtures and improvements to the parking lot and entrances at the Temporary Lodging Facility, stripping and excavating in preparation for foundation work, drilling and blasting within Pond B1, the installation of power lines and road construction.

What's coming next:

Operation of the Temporary Effluent Water Treatment Plant located South of Hardrock Road continues to be underway with discharge of clean water into Kenogamisis Lake. Early Earth Works in the Kenogamisis Pit located North of Highway 11 behind Between Bridges Inn continues with loading and hauling of pit run material to the future Process Plant Site (PPS) area. The Temporary Lodging Facility (TLF) is occupied by construction workforce residents. Exterior and interior finishes within Phase 2 TLF modules is complete while the installation of light fixtures and improvements to the parking lot and entrances continues.  Temporary Power Line work continues with the installation of power lines along the future Plant Site Access Road and the future Tailings Management Facility Access Road.  Construction of Pond B1 within the PPS area continues with blasting and material removal within the Pond B1 footprint. Stripping, excavation, and backfilling work to prepare the foundation for the future Administration Building continues while stripping and excavation work will continue to prepare the foundation for the future Mill and Truck Shop. On-going hauling of material from the S4 Aggregate Pit to the future Tailings Management Facility (TMF) area continues. Erection of the Communications Tower located between Lahtis Road and the PPS will continue. Construction of TMF Access Roads between the S4 Aggregate Pit and the future Haul Road in addition to the construction of access roads between the S4 Aggregate Pit and the future Goldfield Creek Diversion Dam continue. Upgrades to culvert A2 on Lahtis Road along the future Goldfield Creek Diversion will continue. Tree clearing activities within the Lahtis Road area in preparation for the construction of the TMF continues.

The Tree Clearing, Early Earth Works within the Kenogamisis and S4 Aggregate Pits, the installation of power lines, the drill and blast program and road construction involve the use of heavy equipment such as: zoom booms, cranes, drills, excavators, skidders, wood chippers, bulldozers, tri-axle haul trucks, articulated trucks and loaders. For health and safety reasons, we wish to caution the general public to limit non-essential traffic within Hardrock Road and the TEWTP area and to follow and obey posted signs across the Project area.

The safety of our employees, contractors and the general public is paramount as we continue to prepare for construction of the Greenstone Mine.